How much it is
The bid bond is 2% of the total value of the procedure stated in the contract notice or invitation.
The contracting authority may, on reasoned grounds, reduce it to 1% or increase it to 4%. In aggregated tenders run by central purchasing bodies, 2% is the maximum.
For temporary groupings, including those not yet formed, the guarantee covers the obligations of each company in the grouping.
The clauses required by law
Waiver of the benefit of prior enforcement against the principal debtor, waiver of the defence under Article 1957, second paragraph, of the Italian Civil Code, and effectiveness within fifteen days of a simple written demand from the contracting authority.
The guarantee must comply with the standard form under Article 117, paragraph 12, be signed electronically and be verifiable online with the issuer.
Term and scope
It is valid for at least 180 days from submission of the tender. The contract notice may set a different term and require the guarantor to undertake to renew it if the contract has not yet been awarded on expiry.
It covers failure to be awarded the contract after the proposed award and failure to sign the contract through the fault of the successful tenderer, as well as cases of adverse anti-mafia information.
The reductions under Article 106, paragraph 8
30% for companies with UNI CEI ISO 9000 quality certification.
50% for micro, small and medium-sized enterprises and for groupings and ordinary consortia made up solely of SMEs, not cumulable with the 30% reduction.
10% where the guarantee is signed electronically and verifiable online, cumulable with the above.
Up to 20% for the certifications and labels listed in Annex II.13, cumulable, to the extent set in the tender documents.
The reductions are applied one after the other on the amount resulting from the previous one, and must be declared when the tender is submitted.
When the wording is not the statutory one
Some clients require their own wording in the tender documents, with wider waivers than those provided for in Article 106: this is the case with the tenders of Terna, with waiver of Articles 1939, 1944 and 1945 of the Italian Civil Code, and with Enel tenders, whose wordings often include Article 1945. We place bid bonds on these wordings too.