Contract guarantees on the Terna, Enel, RFI and Anas wordings

Guarantees for participation in tenders and for the performance of public works, services and supply contracts, compliant with Legislative Decree 36/2023 and with the wordings required by contracting authorities.

We support the company in reading the tender wordings and in placing them with insurers specialising in the suretyship class.

CLIENTS WITH THEIR OWN WORDINGS

Anas contract guarantees

Guarantees compliant with the Public Contracts Code and with Anas tender documents.

RFI contract guarantees – Rete Ferroviaria Italiana

Guarantees compliant with RFI tender rules for participation and performance: in many RFI tenders the ministerial standard forms apply, while in others the performance bond follows RFI's own General Conditions of Contract, as an independent guarantee. We read the tender rules for every procedure before placing the guarantee. See the RFI guarantee page →

Holy See and Vatican contract guarantees

Guarantees for tenders and contracts of the bodies of the Holy See and of the Governorate of Vatican City State, on the wording required by the tender documents. See the page →

Trenitalia contract guarantees

Guarantees compliant with the wording required by Trenitalia in the tender documents, including in the form of an independent guarantee.

Terna contract guarantees

Independent guarantee on the wording issued by Terna, with waiver of the benefit of prior enforcement (Article 1944, paragraph 2, of the Italian Civil Code) and of the defences under Article 1945.

See the Terna guarantee page →

Enel contract guarantees

On-demand financial guarantee in favour of Enel, provided for by the Group's General Conditions of Contract, including against advance payments. See the Enel guarantee page →

ASTRAL contract guarantees – Lazio Region

Guarantees for works contracts on the regional road network and for the nine-year award, in lots, of road-based local public transport.

Italferr contract guarantees

Guarantees compliant with the wordings required by Italferr in the tender documents.

Social housing contract guarantees (IACP, ATC)

Guarantees for construction, maintenance and refurbishment contracts in social housing, tendered by the Italian public housing institutes (IACP) and the regional housing agencies (ATC).

CONSIP contract guarantees

Guarantees for CONSIP tenders, conventions and framework agreements.

Legal references (2)
  • Tenders run by central purchasing bodies: the bid bond is set in the contract notice at a maximum of 2%, with only the reductions under Article 106, paragraph 8; the performance bond is 10% (Article 117, paragraph 1).
  • Framework agreements: performance bond of up to 2% of the value of the agreement; for call-off contracts it may be lower than 10% (Article 117, paragraph 1).
CONTRACTS ABROAD

Guarantees for contracts abroad

  • Performance Bond: the equivalent of the Italian cauzione definitiva.
  • Advance Payment Bond: the equivalent of the Italian advance payment guarantee.
  • Retention Money Bond: the equivalent of the release of contractual retentions.
  • Maintenance Bond: covering defects that emerge during the maintenance period as a result of faulty workmanship or materials.

Guarantees for tenders in European Union countries

Bid and performance guarantees for public tenders in European Union countries.

CONSTRUCTION SITE COVER

CAR and inherent defects cover

Contractors' All Risks cover and ten-year inherent defects indemnity cover, set according to the type of project. See the construction site page

OTHER GUARANTEES FOR PUBLIC CONTRACTS

Guarantees for private contracts and subcontracts

Advance payments, due performance, release of retentions and proper functioning in contracts between private parties: see the page Private contracts.

Project finance guarantees

Guarantees for project finance procedures, from the bid to the operation of the works.

Legal references (2)
  • Article 193 of Legislative Decree 36/2023: bid bond for all tenders, including that of the promoter; performance bond for the successful tenderer.
  • From the start of operation, a bond renewable annually equal to 10% of the annual operating cost, covering penalties relating to the operation.

Guarantee for works of particular value

Guarantees for general contractor awards and, where the contract notice so provides, for contracts above 100 million euro.

Legal references (2)
  • Article 118 of Legislative Decree 36/2023: in place of the performance bond, a due performance guarantee of a fixed 5% of the contract value and a termination guarantee of 10% of the contract value, up to a maximum of 100 million euro.
  • Waiver of the benefit of prior enforcement (Article 1944 of the Italian Civil Code) and of the defence under Article 1957, paragraph 2; payment within 30 days of written demand.

Assistance with the release of guarantees

We handle requests for the release and reduction of guarantees in force. The performance bond is reduced automatically as the works advance, up to 80%, once the interim progress certificates have been provided to the guarantor. The balance remains in force until provisional acceptance or the certificate of proper execution, and in any event for no more than twelve months from completion of the works (Article 117 of Legislative Decree 36/2023).

GUARANTEES FOR THE TENDER AND FOR THE CONTRACT

Bid bond for public tenders

For participation in the tender procedure. More on the bid bond →

Legal references (5)
  • Article 106 of Legislative Decree 36/2023: 2% of the total value of the procedure stated in the contract notice or invitation; the contracting authority may reduce it to 1% or increase it to 4%.
  • Valid for at least 180 days from submission of the tender.
  • The guarantee provides for waiver of the benefit of prior enforcement (Article 1944 of the Italian Civil Code) and of the defence under Article 1957, paragraph 2, and takes effect within 15 days of written demand.
  • Reductions (Article 106, paragraph 8): 30% with quality certification, 50% for micro, small and medium-sized enterprises (not cumulable with the 30%), 10% for an electronic guarantee verifiable online, up to 20% for the certifications listed in the contract notice.
  • Below threshold (Article 53): not required, save for particular needs in the procedures under Article 50, paragraph 1, letters c), d) and e); in that case it does not exceed 1%.

Performance bond

Covers due performance of the contract by the successful tenderer. More on the performance bond →

Legal references (4)
  • Article 117 of Legislative Decree 36/2023: 10% of the contract value, increased where the tender discount exceeds 10%.
  • The guarantee provides for waiver of the benefit of prior enforcement (Article 1944 of the Italian Civil Code) and of the defence under Article 1957, paragraph 2, and takes effect within 15 days of written demand.
  • Progressive and automatic release in line with performance, up to 80% of the guaranteed amount, once the interim progress certificates have been provided to the guarantor (Article 117, paragraph 8).
  • Below threshold (Article 53): 5% of the contract value, without the increases for the tender discount and without the reductions under Article 106, paragraph 8 (Article 53, paragraph 4-bis); on reasoned grounds the contracting authority may dispense with it.

Advance payment bond

Covers recovery of the advance payment granted to the contractor on the contract price. More on the advance payment bond →

Legal references (2)
  • Article 125 of Legislative Decree 36/2023: advance payment of 20%, which may be raised to 30% in the tender documents.
  • Guarantee equal to the advance payment plus statutory interest for the recovery period, reduced gradually and automatically as the advance is recovered.

Final balance bond

Covers payment of the final balance to the contractor before acceptance or the conformity assessment becomes final.

Legal references (1)
  • Article 117, paragraph 9, of Legislative Decree 36/2023: the guarantee for the final balance is equal to the balance plus statutory interest, until acceptance or the conformity assessment becomes final.
FREQUENTLY ASKED QUESTIONS

Guarantees for public contracts: frequently asked questions

How much is the bid bond for a public tender?

2% of the value of the procedure stated in the contract notice or invitation; the contracting authority may reduce it to 1% or increase it to 4% (Article 106 of Legislative Decree 36/2023). It must remain valid for at least 180 days from submission of the tender. Reductions are available (Article 106, paragraph 8): 30% with quality certification and 50% for micro, small and medium-sized enterprises, which are not cumulable with each other; a further 10% where the guarantee is issued and signed electronically and can be verified online; and up to a further 20% for the certifications and labels listed in Annex II.13. Cumulable reductions are applied in sequence, each on the amount already reduced.

How much is the performance bond and when is it released?

10% of the contract value, increased where the tender discount exceeds 10% (Article 117 of Legislative Decree 36/2023). It is released progressively as the works advance, up to 80%, on providing the guarantor with the interim progress certificates; the balance remains in force until provisional acceptance or the certificate of proper execution, and in any event for no more than twelve months from completion.

Do you place guarantees on the wordings required by Terna or Enel?

Yes. For Terna this is an independent guarantee on the wording issued by Terna, with waiver of the benefit of prior enforcement (Article 1944, paragraph 2, of the Italian Civil Code) and of the defences under Article 1945; for Enel it is an on-demand guarantee provided for by the Group's General Conditions of Contract, including against advance payments. We place these wordings with the insurers on our panel that underwrite them.

What makes a guarantee wording "demanding"?

In public procurement, waiver of prior enforcement (Article 1944 of the Italian Civil Code) is now the rule. Increasingly, however, clients ask for more: waiver of the defences under Article 1945 and derogation from Article 1939 which, together with the clause for payment on first demand and without defences, lead the relationship to be classified as an independent guarantee, detached from the underlying contract; derogation from the time limits of Article 1957; or a standard form of the client's own (Terna, Enel, GSE, MUR) to be accepted as it stands. These are the wordings that many insurers will not underwrite and that we take into direct negotiation with underwriting departments.

Do you also provide guarantees for below-threshold contracts and for advance payments?

Yes. Below threshold, the performance bond, where required, is 5% of the contract value (Article 53, paragraph 4, of Legislative Decree 36/2023); neither the reductions under Article 106, paragraph 8, nor the increases for the tender discount under Article 117, paragraph 2, apply to below-threshold bid and performance bonds (Article 53, paragraph 4-bis); the bid bond is generally not required. For advance payments (20% of the price, which may be raised to 30% in the tender documents) the guarantee covers the amount advanced plus statutory interest (Article 125).

What determines the rate of a surety bond?

It depends on the amount and term of the guarantee, the type of bond, the wording required by the beneficiary and the company's financial position. For the same wording, terms vary from insurer to insurer: for public contract bonds we already know which insurers underwrite each wording, and the case goes straight to the underwriting department for the best rate available in the market.

Surety bonds and guarantees.