The performance bond in public contracts

The performance guarantee that the successful tenderer provides in order to sign the contract, governed by Article 117 of the Public Contracts Code (Legislative Decree 36/2023). We also place it on the major clients' own wordings.

How much it is

The performance bond is 10% of the contract value.

Where the tender discount exceeds 10%, the guarantee increases by one percentage point for each point above 10%; above a 20% discount, the increase is two points for each point in excess.

Under framework agreements the guarantee from all successful tenderers is at most 2% of the value of the agreement; for call-off contracts it may be set below 10%.

The same reductions that apply to the bid bond under Article 106, paragraph 8, apply here.

What it covers and for how long

It covers performance of all the obligations under the contract, compensation for loss arising from non-performance and reimbursement of sums overpaid to the contractor.

It ends with the provisional acceptance certificate or the certificate of proper execution. If it is not provided, the award lapses and the contracting authority calls the bid bond.

The clauses required by law

Waiver of the benefit of prior enforcement against the principal debtor, waiver of the defence under Article 1957, second paragraph, of the Italian Civil Code, and effectiveness within fifteen days of a written demand from the contracting authority.

The guarantee follows the standard forms approved by ministerial decree and may be issued jointly by several guarantors, who appoint a lead guarantor. In temporary groupings it is provided by the lead company on behalf of all the member companies.

Progressive release

The guarantee is reduced as performance advances, up to 80% of the initial amount, automatically: it is enough to provide the guarantor with the interim progress certificates or equivalent documents. This applies to services and supplies too.

The balance remains in force until provisional acceptance or the certificate of proper execution, and in any event for no more than twelve months from completion.

Payment of the final balance requires a guarantee equal to that balance, plus statutory interest for the period from provisional acceptance, or the conformity assessment, until it becomes final.

When the wording is the client's own

Some major clients require the performance bond on a wording of their own, with wider waivers than those set by law: this is the case with Terna, with waiver of Articles 1939, 1944 and 1945 of the Italian Civil Code, and with Enel, whose wordings often include Article 1945.

RELATED POLICIES

Before and during the contract

FREQUENTLY ASKED QUESTIONS

The performance bond: frequently asked questions

How much is the performance bond?

10% of the contract value. Where the tender discount exceeds 10% it increases by one point for each point in excess, and above 20% by two points for each point in excess (Article 117, paragraphs 1 and 2, of Legislative Decree 36/2023).

How is the performance bond released?

Progressively, as performance advances, up to 80% of the initial amount, on providing the guarantor with the interim progress certificates. The balance remains in force until provisional acceptance or the certificate of proper execution, and in any event for no more than twelve months from completion.

How much is the guarantee under a framework agreement?

At most 2% of the value of the framework agreement for all successful tenderers; for call-off contracts the contracting authority may set it below 10%.

Do you place performance bonds on the Terna and Enel wordings?

Yes, including on the major clients' own wordings, with the wider waivers that they require compared with the statutory text.