Construction and restoration
The guarantees may relate to two different stages: building the authorised plant, and decommissioning with restoration of the site at the end of operation. In Apulia, for example, both are required; under national law the guarantee relates to decommissioning and restoration.
Legislative Decree 190/2024
Bond in favour of the Municipality for works carried out freely on undeveloped land (Article 7).
Surety policy covering the cost of the restoration plan, before works begin, under the simplified authorisation procedure (Article 8).
Under the single authorisation, financial guarantees for decommissioning and site restoration must be provided by the deadline stated in the authorisation and in any event no later than 120 days from its issue, on pain of forfeiture, on the basis of the detailed cost calculation set out in the measure (Article 9, paragraphs 10 and 11, as amended by Legislative Decree 178/2025).
National guidelines
The national guidelines (Ministerial Decree of 10 September 2010) provide for a guarantee covering the site restoration works.
The Regions
Apulia (Regional Law 31/2008, Article 4(2)): two guarantees payable on first demand lodged with the Region, one covering construction of the plant and one covering restoration of the site at the end of operation, on pain of forfeiture of the single authorisation. The Constitutional Court upheld their lawfulness (judgment no. 14/2018).
Sicilian Region (DDG 1245/2026): in favour of the Region, equal to the value of the restoration works in the approved project, with a five-year term and renewal.
Agrivoltaics and incentives
The guarantees for GSE grants and incentives (PNRR agrivoltaics, biomethane, CACER) are on the page GSE guarantee.